Market Intelligence Report

    Winning Sewer Rehab Contracts

    A Contractor's Field Guide to Public Procurement in Florida

    May 202640 Min Read22 PagesVersion 1.0

    Key Findings

    $200K

    Florida Public Construction Bonding Threshold under F.S. 255.05

    72 Hours

    Window to File a Bid Protest Notice on State Procurements, F.S. 120.57(3)

    5%

    Maximum Retainage on Florida Government Construction Contracts

    25 Days

    Business Days for Local Government to Pay Contractor Invoices

    Up to 30%

    Estimated Labor Cost Premium When Prevailing Wages Apply

    $30M

    Miami-Dade County-Wide CIPP Contract Issued in 2024

    Executive Summary

    The municipal sewer rehabilitation market is a relationship business disguised as a low-bid market. The engineer of record, selected under qualifications-based statutes like Florida's Consultants' Competitive Negotiation Act (F.S. 287.055), writes the specifications, evaluates the bids, recommends award, and approves pay applications. Contractors who treat municipal work as a pure pricing exercise lose money. Those who track engineering firm task-order pipelines, FDEP State Revolving Fund priority lists, and consent-order milestones see the work coming 12 to 24 months before it hits any bid platform.

    The compliance stack is the moat. A credible municipal CIPP, pipe bursting, or manhole rehabilitation contractor in Florida needs a Certified Underground Utility and Excavation Contractor license, at least $1 million of single-job bonding capacity from a Treasury-listed surety, NASSCO PACP/MACP/LACP certification on the crew, E-Verify enrollment, and Davis-Bacon-capable certified payroll if pursuing SRF or IIJA-funded work. Contractors lacking any one of these are non-responsive on most municipal solicitations.

    This report is a practical field guide to every step of that process: how municipal sewer rehabilitation work gets procured in Florida, where to find bid opportunities before they're advertised, what compliance requirements gate access to the market, how proposals are actually evaluated, why the engineer of record is your most important relationship, and a tiered roadmap for contractors at every revenue level. All statutory citations are current as of the 2025 Florida Statutes.

    Section 01

    How Sewer Rehab Work Gets Procured

    A typical Florida municipal sewer rehabilitation project moves through six phases: need identification (FDEP consent order, sanitary sewer evaluation study, master plan, capital improvement program, rate study, or wet-weather model output); engineer-of-record selection under CCNA; design and specification development, often using NASSCO performance specifications as a starting point; advertising via the utility's procurement portal; evaluation and award; and notice to proceed.

    State Vs. Local Procurement: a Critical Distinction

    Florida Statutes Chapter 287 (F.S. 287.057) governs procurement for state agencies, defined as the executive branch of state government. It does not govern counties, municipalities, school boards, or special districts. For the vast majority of sewer rehabilitation contracts, which are issued by cities, counties, and utility authorities, the procurement framework is local-ordinance-driven. Miami-Dade has Section 2-8.1, Broward has Section 21, and JEA, Tampa, and Orlando each maintain their own procurement codes.

    However, several state-law overlays apply to all Florida local government construction procurement. F.S. 287.055 (CCNA) governs how engineers are selected. F.S. 255.05 governs bonding. F.S. 255.103 governs Construction Manager at Risk. F.S. 218.735 governs prompt payment. F.S. 255.20 governs competitive bidding thresholds for public construction. Understanding which statute applies to your specific solicitation is the first step to avoiding disqualification.

    Three Primary Procurement Methods

    Most Florida municipalities and utilities use three solicitation methods for construction. An Invitation to Bid (ITB), also called a sealed competitive bid, is used when the agency can fully define scope and specifications. Award goes to the lowest responsive, responsible bidder. The vast majority of unit-priced CIPP, pipe bursting, and manhole rehabilitation contracts are awarded this way. A Request for Proposals (RFP) is used when scope cannot be fully defined or the agency wants a qualitative best-value selection, with price as one factor among several. Common for design-build and complex multi-method rehabilitation programs. An Invitation to Negotiate (ITN) is used when negotiations may be necessary to obtain best value and is less common for trenchless rehabilitation contracts.

    CMAR Delivery

    Florida agencies are increasingly using Construction Manager at Risk (F.S. 255.103) for larger wastewater rehabilitation programs. The City of Crystal River, City of Winter Springs, City of Minneola, Hillsborough County Water Resources, and JEA all have active CMAR procurements. CMAR is a qualifications-based selection: the agency selects the CM during preconstruction, the CM provides constructability and cost feedback during design, then converts to a Guaranteed Maximum Price holding all subcontracts. For a trenchless specialist, this is critical: CMAR primes are typically large general contractors who self-perform little or no CIPP, pipe bursting, or lining work. Trenchless subs win task orders by being on the CMAR''s qualified-bidder list rather than by responding to public IFBs.

    Contract Structures & Change Orders

    Sewer rehabilitation contracts are overwhelmingly unit-price: linear feet of CIPP by diameter, count of point repairs, count of manholes lined, count of lateral seals. Lump sum is used for mobilization, maintenance of traffic, demobilization, and bonds/insurance. GMP appears in CMAR. Florida public agencies generally have written change-order authority thresholds (often $50,000 to $250,000 for staff approval, above that requiring commission approval). A written change order must be approved before the work is performed. Contractors lose change-order claims most often by failing to document changed conditions in writing within the time windows specified in the General Conditions.

    Section 02

    Where to Find Municipal Bid Opportunities

    No single platform covers Florida comprehensively. The minimum effective coverage requires registration on DemandStar (the dominant network for Florida cities and counties, with over 1,400 government agencies posting directly), BidNet Direct (broader Southeast coverage), MyFloridaMarketPlace/VendorLink (for state agency procurements), and individual municipal portals. Miami-Dade County (Strategic Procurement Department), Hillsborough County, City of Orlando, and JEA each maintain their own portals. Some are duplicated to DemandStar but not all. GovWin IQ from Deltek provides premium pre-solicitation intelligence but costs $5,000 to $15,000+ per year.

    Forward-Looking Pipeline Tools

    Contractors who win consistently look beyond bid platforms. FDEP publishes CWSRF and DWSRF priority lists quarterly (second Wednesdays of August, November, February, and May) at floridadep.gov. Each listing includes project sponsor, project description, funding amount, and engineer of record. A contractor who tracks the priority list will see a funded rehabilitation project 6 to 18 months before bid advertisement.

    Adopted utility Capital Improvement Programs and rate studies are public documents. Every Florida utility publishes a 5 to 10 year CIP with annual funding for sewer rehabilitation or I&I reduction. Reading the budget reveals the funded linear footage for the next year. FDEP consent orders and stipulated penalty correspondence, published on DEP''s Oculus document site, contain milestone schedules that predict bid timing. A utility under consent order to rehabilitate a specified number of linear feet by a specific date will issue procurement roughly 9 to 12 months in advance.

    Engineering firm task-order pipelines are the highest-value lead source. Once you know the engineer of record on a continuing-services contract (often disclosed on the SRF priority list), the task orders being authorized are the upcoming bids. Florida ACEC chapter newsletters, FWEA conference presentations, and engineering firm project portfolios all reveal active rehabilitation programs.

    Trade Publications & Conferences

    Trenchless Technology and Underground Construction magazines cover bid trends and contractor news. Key venues for engineer and contractor relationship building: the No-Dig Show (NASTT, annual), WEFTEC (annual, October), NASTT regional events (Southeast/Florida chapter), the Florida Water Resources Conference (FWEA/AWWA-FL), and Florida Stormwater Association events.

    Section 03

    Bidding Requirements & Compliance

    Bonding under F.S. 255.05

    Florida''s Little Miller Act requires a payment and performance bond from any contractor entering a formal contract with the state, county, city, or political subdivision for construction of a public building or work at any project value over $200,000. Below $100,000, no bond is statutorily required. Between $100,000 and $200,000, the public entity has discretion to waive. Above $200,000, bonds are mandatory and must be recorded in the public records of the county where the project is located. The bond must reference F.S. 255.05 on its face. There is no mechanic''s lien on public property in Florida. Subcontractor payment recovery runs exclusively through the payment-bond claim process: a notice of nonpayment must be served on both the contractor and surety no earlier than 45 days and no later than 90 days after final furnishing, with suit filed within 1 year.

    Establishing Bonding Capacity

    Sureties evaluate capacity (working capital, equipment, technical staff), capital (net worth, liquidity), and character (credit, claims history). Standard surety underwriting commonly approves single-job bonds at roughly 10 times working capital and 10 times net worth, with aggregate programs at approximately 20 times working capital. The SBA Surety Bond Guarantee Program is the entry point for emerging contractors: it guarantees 80% to 90% of surety loss and supports individual contracts up to $9 million (non-federal) or $14 million (federal). A trenchless contractor planning to bid municipal work should aim for at least $1 million single-job capacity and $5 million to $10 million aggregate before pursuing a Florida county-scale contract.

    Insurance

    Typical Florida municipal minimums for sewer rehabilitation: $1 million per-occurrence / $2 million aggregate Commercial General Liability; $1 million Auto; statutory Workers'' Compensation; $5 million Umbrella/Excess (common for projects above $500,000); and Pollution Liability of $1 million to $5 million (now standard given the styrene release history of CIPP). Specifications typically require additional-insured endorsements for the owner and engineer of record.

    Florida Licensing

    Underground utility and excavation work in Florida requires a Certified Underground Utility and Excavation Contractor (CUC) license from the DBPR Construction Industry Licensing Board (F.S. 489.105). The scope expressly includes directional drilling, auger boring, jacking and boring, trenchless technologies, and slip lining of sanitary sewer collection systems. Requirements include passing the trade-knowledge exam (80 questions, 5 hours) and the Business and Finance exam (120 to 125 questions, 6.5 hours), both open-book at 70% passing. Four years of experience including one year as a foreman is required, with college credits substituting for up to three years. A FICO score of 660 or higher is required, or the applicant must post a $20,000 surety bond. Minimum GL of $100,000 bodily injury and $25,000 property damage is required. License renewal requires 14 hours of continuing education every two years. Every Florida municipality also requires a local Business Tax Receipt, and many require a separate municipal contractor registration.

    DBE / Mbe / Wbe Requirements

    EPA''s Disadvantaged Business Enterprise rule (40 CFR Part 33) governs SRF-funded and other federally funded EPA infrastructure work. Public Law 102-389 establishes a combined 8% MBE/WBE national participation objective. EPA recipients negotiate separate MBE and WBE fair share objectives for each procurement category (construction, equipment, services, supplies) per 40 CFR Section 33.401. The DBE rule is a goal, not a quota, but prime contractors must demonstrate six good-faith efforts: make DBEs aware of opportunities, divide work into smaller tasks where feasible, advertise to DBEs, provide adequate response time, document outreach, and require subcontractors to take the same steps. Reporting is on EPA Form 5700-52A annually for any agreement above the $350,000 Simplified Acquisition Threshold. A contractor pursuing SRF-funded work who fails to document good-faith efforts is at material risk of contract default.

    Build America, Buy America (Baba)

    BABA (Section 70914 of P.L. 117-58, effective May 14, 2022) permanently applies to all equivalency SRF projects and to all WIFIA projects. All iron, steel, manufactured products, and construction materials must be U.S.-produced unless waived. The American Iron and Steel (AIS) requirement continues for non-equivalency SRF projects. EPA has issued limited waivers including a de minimis waiver (5% of total project cost), a small-project waiver (under $250,000 total), and an adjustment-period waiver that has been amended and effectively sunsets for projects funded with State Fiscal Year 2025 and later capitalization grants. For any 2026 contract pursuit, contractors should plan for full BABA compliance. Standard practice: require BABA/AIS certifications from your CIPP material supplier as a procurement document on every bid response.

    E-Verify

    F.S. 448.095 (effective January 1, 2021) requires every Florida public employer, contractor, and subcontractor to enroll in E-Verify for all new hires. Subcontractors must provide affidavits to primes. Since SB 1718 (effective July 1, 2023), private employers with 25 or more employees are also required. Penalties include $1,000 per day fines after a third violation in any 24 months, Florida Department of Commerce (formerly DEO) license action, DBPR license suspension, and mandatory contract termination if the public agency forms a good faith belief of a violation, with no cure period.

    Section 04

    Prevailing Wage & Certified Payroll

    The Davis-Bacon Act (40 U.S.C. Section 3141 et seq.) applies to federal construction contracts above $2,000 and to federally funded or assisted construction projects. Since the FY2012 EPA appropriations, Davis-Bacon prevailing wages apply permanently to all CWSRF and DWSRF projects funded in FY2012 or later, including state match. The Bipartisan Infrastructure Law extends and reinforces this.

    Florida has no state prevailing wage law. The original 1933 statute was repealed in 1979. There is no state-level prevailing wage exposure on Florida-only-funded work. This makes Davis-Bacon coverage on SRF and IIJA projects an outsized cost differential, because contractors move from genuinely low Florida non-union market wages to federally determined rates, typically adding 15% to 30% to labor cost and roughly 10% to 25% to total bid price.

    Reading a Wage Determination

    The Department of Labor publishes wage determinations by county and construction type (Building, Heavy, Highway, Residential). Sewer rehabilitation is generally classified as Heavy construction. The determination lists a basic hourly rate plus a fringe benefit rate for each classification. Classifications typically applied to a CIPP crew: Laborers (Group 1 for general, higher groups for skilled tasks), Power Equipment Operators, Truck Drivers, and sometimes Pipefitter or Plumber for connection work. There is no specific CIPP installer classification in most determinations. Contractors apply the laborer or operator rate appropriate to the actual work and document this in conformance requests where necessary.

    Certified Payroll: WH-347

    The Copeland Act (40 U.S.C. Section 3145) and 29 CFR 5.5(a)(3)(ii) require weekly certified payrolls. Form WH-347 is the functionally standard format. Each weekly submission must include a signed Statement of Compliance, a list of every laborer or mechanic working that week with hours by day, classification, hourly rate, fringe credits, gross earned, deductions, and net paid. False statements on a WH-347 are subject to 18 U.S.C. Section 1001 and 31 U.S.C. Section 3729 (False Claims Act). Common errors that trigger investigation include classification mismatches, improper fringe benefit credit, missing apprentice registration, and arithmetic errors on overtime.

    Setting Up Davis-Bacon Payroll

    Assign a job number to each Davis-Bacon project and segregate cost coding. Require timekeeping that captures classification by hour, not just by day. Calculate fringe credits separately for each fringe type. Use certified payroll software that generates WH-347 from time data (LCPtracker, eMars, Foundation Software, Hammr, Sage, or QuickBooks with a payroll add-on). Train one designated person to review every payroll before submission. Set this up before you need it. Contractors who try to retrofit Davis-Bacon payroll mid-project consistently make classification and fringe errors that result in back-wage findings.

    Section 05

    How Proposals Are Actually Evaluated

    Low-Bid IFB Evaluation

    Two sequential reviews determine the winner. Responsiveness asks whether the bid materially complies with the solicitation: bid bond present, all forms signed, math correct, no conditional bids, submitted on time. Responsibility asks whether the bidder is financially capable, properly licensed, with adequate experience and bonding. Common reasons bids are rejected as non-responsive include missing or improperly executed bid bond, failure to acknowledge addenda, unsigned bid form, unbalanced unit prices, conditional or qualified bids, failure to list required subcontractors, failure to submit DBE/SBE participation forms, and late submission. Florida agencies are strict: 3:00:01 p.m. on a 3:00 p.m. deadline is non-responsive.

    RFP Evaluation Criteria

    When a Florida agency uses an RFP for a sewer rehabilitation program, typical weighting runs approximately: qualifications and relevant experience at 25% to 35%, technical approach and methodology at 20% to 30%, price or cost at 20% to 30%, project schedule and ability to perform at 10% to 15%, references and past performance at 5% to 10%, and DBE/SBE participation at 5% to 10%. These weights are illustrative; each solicitation is unique and contractors must read the evaluation criteria in the document.

    Table 01. Typical RFP evaluation criteria weighting for Florida municipal sewer rehabilitation programs (illustrative ranges)

    Qualifications and experience

    Typical Weight:
    25%-35%
    What Evaluators Look For
    • Specifically relevant municipal CIPP/bursting projects
    • NASSCO certifications on named personnel
    • Safety record (EMR below 1.0)

    Technical approach

    Typical Weight:
    20%-30%
    What Evaluators Look For
    • Project-specific methodology, not generic boilerplate
    • Understanding of site conditions, bypass pumping, MOT

    Price/cost

    Typical Weight:
    20%-30%
    What Evaluators Look For
    • Competitive but realistic
    • Unbalanced or front-loaded bids flagged

    Schedule and ability to perform

    Typical Weight:
    10%-15%
    What Evaluators Look For
    • Equipment ownership vs. rental
    • Crew availability
    • Concurrent project load

    References and past performance

    Typical Weight:
    5%-10%
    What Evaluators Look For
    • Verifiable contacts
    • Owner satisfaction
    • On-time/on-budget history

    DBE/SBE participation

    Typical Weight:
    5%-10%
    What Evaluators Look For
    Named subcontractors/suppliers with documented good-faith efforts

    What Evaluators Look for in a Trenchless Contractor

    Specifically relevant municipal CIPP, pipe bursting, or manhole experience (residential CIPP experience is heavily discounted). NASSCO PACP/MACP/LACP and ITCP-CIPP certifications on named project personnel. Crew certifications (CDL, OSHA 30, confined space, traffic control). Equipment ownership versus rental, with owned equipment scoring higher on schedule reliability. Safety record with EMR below 1.0 strongly preferred. Bonding capacity letter from a Treasury-listed surety. Audited or reviewed financial statements for the last three years. A project list with reference contacts, not just project names. A DBE/SBE/WBE participation plan with named subcontractors and suppliers. A technical approach that demonstrates understanding of this specific project; generic boilerplate is heavily penalized.

    Bid Protests

    Under F.S. 120.57(3), a notice of protest must be filed within 72 hours of award posting (excluding weekends and Florida state holidays). This deadline is jurisdictional. A formal written protest follows within 10 calendar days, plus a protest bond. Filing triggers an automatic stay of the procurement. The agency must convene a settlement conference within 7 business days. If unresolved, the matter goes to the Division of Administrative Hearings for a hearing within 30 days. The standard of review is whether the agency''s action was clearly erroneous, contrary to competition, arbitrary, or capricious. Important: these timelines apply to state agency procurements under the Administrative Procedure Act. Local government bid protests follow local procurement codes, which often but not always mirror the 72-hour/10-day framework. Some local codes use shorter or different windows. Always check the specific solicitation''s protest procedures.

    Section 06

    The Engineering Firm Relationship

    In a Florida municipal sewer rehabilitation project, the engineer of record (selected under CCNA, often holding a continuing-services contract) typically writes the technical specifications, participates in or chairs the evaluation committee, recommends award, issues the notice to proceed, reviews and approves submittals, inspects work through their resident project representative, approves or rejects pay applications, decides whether changed conditions justify a change order, and signs off on substantial completion and final acceptance. A contractor who is on the wrong side of the engineer's opinion will lose money on the project regardless of the contract price.

    Identifying the Right Engineering Firms

    Major Florida engineering firms active in sewer rehabilitation include Hazen and Sawyer (Miami-Dade WASD, Fort Lauderdale CO program management), Jones Edmunds (Gainesville-based, north and central Florida), CDM Smith, Jacobs, Brown and Caldwell, Carollo, Wade Trim (Pinellas County WWCSMP), McKim and Creed (Pinellas flow monitoring), RS&H (FDEP post-hurricane SSO evaluation), Kimley-Horn, Ardurra, Stantec, and Black and Veatch. The FDEP SRF priority list and bid advertisements both name the engineer of record. Track these to identify which firm has which utility''s continuing-services contract.

    Building Relationships Before Bid Day

    The continuing-services and task-order model means an engineer often selects or strongly influences the selection of the contractor for individual task orders within a multi-year program. Attend every pre-bid meeting in your region, even on projects you don''t intend to bid. Engineers track who shows up. Request to be on the engineer''s notification list for upcoming solicitations. Offer technical input during the design phase when permitted. Speak or sponsor at FWEA, Florida Water Resources Conference, and NASTT regional events where engineers present. Provide feedback on draft NASSCO specifications when shared. Maintain a clean track record on every engineer''s projects; one bad project with one engineer in Florida''s tight municipal water community will follow you for years.

    What Engineers Look For

    Technical precision in submittals (correct ASTM references, calculations stamped by a Florida P.E.), on-time and complete pay applications, proactive change-order documentation rather than end-of-project surprise claims, responsive communication, and absence of NASSCO PACP-coded defects in post-installation CCTV.

    Section 07

    Contract Administration After Award

    Notice to Proceed & Submittals

    The notice to proceed starts the contract clock. Mobilization is typically required within 7 to 14 days. Material submittals include liner manufacturer data, resin technical data sheets, ASTM test data (typically per ASTM F1216 for inversion-cured CIPP, F1743 for pulled-in-place, F2019 for fiberglass UV-cured), design calculations stamped by a Florida P.E., wet-out facility certifications, bypass pumping plan, and CCTV inspection methodology. The engineer typically has 14 to 30 days to review.

    Inspection & Testing

    Standard municipal CIPP testing per NASSCO performance specifications: pre-installation CCTV by PACP-certified personnel, post-installation CCTV showing the liner is continuous and tight-fitting with all service connections reinstated (typically to 90% to 95% of original opening area, with many Florida utilities including Miami-Dade WASD requiring 95% or higher), and sample testing per ASTM D790 (flexural) and D638 (tensile) by an independent laboratory. Many specifications include a payment-deduction schedule for thickness or property failures.

    Pay Applications & Prompt Payment

    Monthly invoicing is the norm. Under F.S. 218.735, the local government must pay within 25 business days of receipt of an approved invoice (or 20 business days if no agent approval is required). Retainage is capped at 5% of each progress payment, established by Ch. 2020-173 (SB 246), effective October 1, 2020. Late payments accrue interest at 2% per month. After 50% completion, the contractor may request release of one-half of accumulated retainage. SB 346 (effective July 1, 2023) requires the local government to develop a punch list within statutory deadlines after substantial completion, or the contractor may invoice the entire remaining balance.

    Warranty

    Standard Florida municipal contracts carry a 1-year general construction warranty. CIPP-specific warranty terms commonly require a 10-year structural warranty on the cured liner, with additional inspection at year 1 or 2. Some specifications require a separate 2-year defect repair guarantee in addition to the structural warranty.

    Liquidated Damages & Lien Rights

    Liquidated damages are common at $500 to $2,000 per calendar day, scaled to project size. Florida has no mechanic''s liens on public property. Subcontractor and supplier recovery is strictly through the F.S. 255.05 payment-bond claim process. Subcontractors who do not preserve their bond claim rights within the 45-day and 90-day notice windows and the 1-year suit limitation have no recovery on Florida public projects.

    Section 08

    Common Mistakes Contractors Make in Municipal Work

    Bidding too low to buy in. The first municipal contract is the hardest to win, and many contractors price below their actual cost to break in. This works only if the loss is honestly capitalized as a marketing expense and the company has the working capital to absorb it. More often, the contractor exhausts working capital on a money-losing first job, cannot fund the second, and exits the market.

    Not reading the full specification. Florida municipal sewer rehabilitation specifications include General Conditions, Supplementary Conditions, and Technical Specifications. The technical specifications often dictate resin type (vinyl ester required for industrial discharge zones), liner thickness method (Class IV partially deteriorated vs. Class V fully deteriorated), cure method (UV cure not permitted on liners over 36 inches), or testing protocols that effectively limit bidders. Contractors who price assuming generic NASSCO specifications and discover restrictive technical requirements after award absorb the cost.

    Missing bid deadlines or submitting incomplete packages. Florida agencies enforce bid deadlines to the second. Bids missing the bid bond, missing required acknowledgments, or with an unsigned bid form are non-responsive without exception.

    Underestimating Davis-Bacon labor costs on SRF-funded projects. A Florida non-union contractor pricing an SRF-funded job at typical Florida market wages will be 15% to 30% under cost on labor and may also miss fringe burdens and certified payroll administrative cost.

    Failing to document changed conditions. Florida municipal contracts require written notice of differing site conditions within tight windows, often 5 to 10 days from discovery. Contractors who say they will work it out at the end lose the change-order claim.

    Not building engineering firm relationships before bid day. Walking in cold to a bid you did not pre-qualify for, with a low number, against contractors the engineer knows, is a structural disadvantage even if you win on price.

    Assuming residential CIPP experience translates directly. Municipal CIPP requires PACP-coded post-CCTV, P.E.-stamped design calculations, ASTM-compliant lab testing, reinstatement of service connections to specification, and Class IV/V structural design. Residential work has no analog for any of these.

    Ignoring DBE requirements and failing to document good-faith efforts. This is the most-cited compliance failure on EPA-funded contracts and a routine basis for withholding final payment.

    Section 09

    Practical Roadmap for Contractors New to Municipal Work

    For Contractors with $0 to $1 Million Annual Revenue

    Get the Florida Underground Utility and Excavation Contractor license now; it is the longest-lead-time item. Join NASTT and FWEA. Attend two FWEA events and one NASTT regional event in the next 12 months. Get NASSCO PACP/MACP certified for two field personnel within 6 months (initial combined certification runs approximately $1,075 for a 3-day course; ITCP-CIPP certification runs $1,375 for a 2-day course; all are valid for 3 years). Establish a surety relationship and target $500,000 to $1 million single-job capacity within 12 months. Pursue subcontract work with 2 to 3 prime contractors holding existing Florida municipal CIPP contracts. Goal: three completed municipal subcontracts in 18 months, totaling 5,000 to 15,000 linear feet of installed CIPP.

    Threshold to graduate to prime bidding: $1 million single-job bonding, three documented municipal subcontracts, NASSCO PACP/MACP/ITCP-CIPP on at least one foreman, audited financial statements for the last two years, and a tested certified payroll system.

    For Contractors with $1 Million to $10 Million Revenue

    Prequalify with the top 3 to 5 utilities in your region within 6 months. Enroll in E-Verify today if not already done. Establish a Davis-Bacon-capable certified payroll system before responding to your first SRF-funded solicitation. Identify the engineer of record for each utility''s continuing-services contract and schedule a meeting with the project manager at each firm within 90 days. Bid only projects where you can document a competitive advantage. Pass on bids that require buying in below cost.

    Threshold to scale into county-level work: $5 million+ aggregate bonding capacity, EMR below 1.0, demonstrated PACP/MACP/LACP-coded post-CCTV deliverables on five completed projects, and a BABA documentation system in place.

    For Contractors with $10 Million+ Revenue

    Pursue CMAR subcontract relationships with the major Florida CMs (PCL, Brasfield and Gorrie, Garney, Hensel Phelps, depending on who holds local contracts). Develop the capacity to self-perform 25,000 to 75,000 linear feet of CIPP per year with redundant crews and a bench of trained foremen. Track FDEP consent orders quarterly and identify utilities approaching milestones 12 to 24 months out. Establish pollution liability of $5 million+ and professional liability if pursuing design-build.

    Threshold to bid IDIQ ceiling work above $20 million: $10 million+ single-job bonding, audited financials, in-house certified payroll administrator, NASSCO ITCP-certified resident project supervisor on every active job, and a BABA/DBE compliance program with documented good-faith effort templates.

    Sources

    25 sources cited in this report

    Sources

    1. 1.
      Florida Statutes, F.S. 287.055 (CCNA)
    2. 2.
      Florida Statutes, F.S. 255.103 (CMAR)
    3. 3.
      Florida Statutes, F.S. 255.05 (Public Construction Bonding)
    4. 4.
      Florida Statutes, F.S. 218.735 (Local Government Prompt Payment)
    5. 5.
      Florida Statutes, F.S. 255.078 (State Government Retainage)
    6. 6.
      Florida Statutes, F.S. 448.095 (E-Verify)
    7. 7.
      Florida Statutes, F.S. 489.105 (Contractor Licensing)
    8. 8.
      F.S. 120.57(3) Bid Protest Procedures (Radey Law analysis)
    9. 9.
      SB 346 (2023): Retainage and Prompt Payment Reforms
    10. 10.
      Ch. 2020-173 (SB 246): 5% Retainage Cap
    11. 11.
      SB 1718 (2023): E-Verify Expansion
    12. 12.
      Florida Construction Legal Updates, CCNA Primer
    13. 13.
      Florida Construction Legal Updates, Payment Bonds
    14. 14.
      Akerman LLP, Florida Procurement Law
    15. 15.
      CRS Report R41469, Davis-Bacon and SRF Programs
    16. 16.
      U.S. DOL, WH-347 Certified Payroll Form
    17. 17.
      EPA, SRF American Iron and Steel Requirement
    18. 18.
      U.S. Dept. of Commerce, Build America Buy America
    19. 19.
      SBA, Surety Bond Guarantee Program
    20. 20.
      SBA, Statutory Increases for SBG Program (Feb. 2024)
    21. 21.
      FDEP, SRF Priority Lists
    22. 22.
      NASSCO, ITCP Certification Program
    23. 23.
      NASSCO, PACP/LACP/MACP Certification
    24. 24.
      Miami-Dade WASD, Insituform Contract S-20076 Board Memo
    25. 25.
      40 CFR Part 33, EPA DBE Program Requirements

    About infraTerra

    infraTerra, Inc. is a pipeline infrastructure intelligence firm. We publish independent market research and build interactive intelligence tools focused on wastewater pipeline infrastructure. Our work is grounded in two decades of field experience, source-verified data, and structural independence from the contractors and agencies whose work we analyze.

    infraterrainc.com  |  support@infraterrainc.com  |  888-880-PIPE

    Insight Beneath. Integrity Above.

    Related Tools

    Talk to infraTerra

    Ready to Pursue Municipal Work?

    infraTerra provides advisory services to trenchless contractors building their municipal contracting capability, from bonding strategy through bid preparation and engineering firm relationship development.

    Or call 888-880-PIPE