    Miami-Dade Revives $38.6M Sewer Plant Bid as Consent Decree Deadline Nears

    Miami-Dade WASD wants to rescind a rejected bid and award $38.6M for Central District plant rehab, citing its June 2028 consent decree deadline.

    infraTerra · October 20, 2026

    The Story

    Miami-Dade County's Water and Sewer Department filed a resolution on October 16 that would rescind its February 2026 rejection of all bids and award Contract S-950 to Poole and Kent Company of Florida for $38,624,490, according to the county's legislative file. The work rehabilitates Return Sludge Pump Stations 1, 2 and 3 and the secondary clarifiers at Plant 01 of the Central District Wastewater Treatment Plant.

    The file shows only two firms bid. The low bidder, Razorback LLC, withdrew two days after bid opening after reporting a pricing error of about $5 million. The engineer of record then found the remaining Poole and Kent bid was 34.30% above its cost estimate, and the county rejected all bids with plans to rebid. WASD later reversed course, citing approaching consent decree deadlines, after an independent review by AECOM found the price reasonable for the scope, duration and operating constraints.

    The project is one of 81 treatment plant line items under the 2014 consent decree Miami-Dade entered with EPA, the State of Florida and FDEP, which has a June 2028 completion date. The county reports about 89% of the program is complete. Funding comes from WASD revenue bonds, and the contract runs 1,705 days.

    Source: Miami-Dade County Legislative Hub, File Number 261836, Resolution rescinding rejection of bids and awarding Contract S-950, October 16, 2026

    Our Perspective

    The infraTerra Take

    Our read: when a consent decree clock gets short, the deadline sets the price. Miami-Dade had two bids, lost one to a bid error, and is now prepared to pay 34.30% over its own engineer's estimate rather than lose more time to a rebid. That is a rational call for the county, and a warning for every Florida utility working under an FDEP or EPA order.

    For utilities and agencies, the lesson is to procure early and procure wide. A two bidder field on a $38 million job leaves no room for error, and every month spent on a rebid is a month taken from the compliance schedule. Packaging, prequalification and industry outreach done a year ahead cost far less than accepting a premium under deadline pressure. The same logic applies to collection system rehab and SSO reduction work tied to any Florida consent order.

    For contractors, two points stand out. First, a single estimating error knocked the apparent low bidder out of a decree driven job, so bid review discipline is a competitive advantage, not overhead. Second, decree deadlines across Florida are creating a seller's market for firms that can show capacity and schedule certainty. Qualified bidders that show up when fields are thin hold real bargaining power. Our guide to winning municipal contracts covers how to position for that work.

    What to Watch

    • Committee hearing on the S-950 award, which the county file lists as pending a November committee
    • The January 20, 2027 agenda date shown in the county file for the item
    • Miami-Dade progress toward its June 2028 consent decree completion date

    More from the infraTerra Take

    View All News
    Capital Projects & Construction

    Miami, Miami-Dade County, FL

    Miami-Dade Septic-to-Sewer Corridor Runs 1,000 Days Late as Costs Climb

    A Miami-Dade sewer corridor on NW 22nd Avenue is 1,000 days late after unforeseen underground conditions, a warning for Florida septic-to-sewer plans.

    October 23, 2026 · WLRN

    • Septic-To-Sewer
    • Miami-Dade
    • WASD
    • Construction Delays

    Talk to infraTerra

    What This Means for Your System

    Talk with infraTerra about how this development affects your utility, agency or business, from funding and compliance to the condition of the pipes you are responsible for.

    Or call 888-880-PIPE