Sioux Center, Iowa replaced about 2 miles of sewer main along Highway 75 while the highway was being rebuilt, according to KSCJ. The old lines were clay, ductile iron and Orangeburg pipe, some more than 100 years old, and were replaced with modern plastic pipe.
The city also replaced 90 service lines running from the main to each customer's right-of-way line. The city's wastewater department reports that inflow and infiltration along the Highway 75 corridor dropped by 95%, according to KSCJ.
A new force main with larger pumps and pipes, built to serve growth, allowed the city to remove an aging lift station near 12th Street SW, KSCJ reports.
Source: KSCJ 1360, Wastewater Updates Under Highway Bring Long-Term Benefits, November 11, 2026
The infraTerra Take
Florida utilities should study this result closely. Sioux Center did not just reline a main. It replaced the main and the public side of every service connection in the same corridor, and it reports a 95% reduction in I&I. Mainline-only programs often fall short of that because groundwater simply finds the next weakest point, and that is frequently the lateral.
The second lesson is timing. The city did the sewer work while the highway was already torn up. Florida has a steady stream of state and county road projects, and each one is a chance to replace or line laterals with far less disruption than coming back later. We recommend utilities flag sewer basins under planned road work and fold lateral work into those contracts before design is locked.
There is a limit to the comparison. Sioux Center's replacement stopped at the right-of-way line, so it did not reach the portion of each line on private property. In Florida's high groundwater basins, that private segment can be a major infiltration path. Our lateral vs. mainline I&I tool lays out how the two compare.
For contractors, corridor projects that bundle mains, service lines and lift station retirement are where scope is heading. For property owners, it shows the public side can be fixed in one pass, and the private side is the next question. Mainline work alone rarely finishes the job.
What to Watch
- Whether Sioux Center reports flow monitoring results through a full wet season to confirm the reduction
- Florida utilities adding public side lateral replacement to upcoming roadway contracts